The key work to unite Malaga and Granada by AVE will finish later this year
The key work to unite Malaga and Granada by AVE will finish later this year
The connection of Malaga and Granada by direct AVE may be a reality at the end of this year or, at the latest, at the beginning of 2021. The key work for this route to be put into service, the new Antequera-Ciudad station, It is already at an execution level of around 80%, after it had to be rescued from the previous contractor (which meant a three-year hiatus) and re-awarded in April 2019, with an execution period that was set in twelve months.