Description
The works have consisted of the control and surveillance and safety and health monitoring of the works of Siphons 4 and 5 of the Canal de Piedras for the replacement, in both siphons, of the existing pipeline of Ø1500 mm with another of Ø2500 of reinforced concrete with sheet metal shirt and with lengths of 200 meters and 250 meters respectively. The objective of the works is the expansion of the hydraulic transport capacity of the siphons nº4 and nº5 of the Piedras canal, so that at least 11 m3 / s can be circulated through both infrastructures.